McBreen Enviro UK was contracted by a new client to carry out trenchless rehabilitation works on a section of ageing concrete pipework. The project required careful coordination, multiple access points, and minimal surface disruption.

Project Scope:

Installation of a UV-cured liner across five sections of 300mm concrete pipe, totalling over 200 metres.

Works Completed:

  • A full CCTV survey was conducted ahead of works to assess access, condition, and alignment
  • UV lining technology was selected for its speed and non-intrusive application
  • All works were completed overnight as per the programme

Result:

  • Over 200m of pipe rehabilitated using no-dig methods
  • Installation delivered in line with specification
  • A smooth, efficient project completed for a new client