Final mechanized tunnelling on the Brenner Base Tunnel successfully completed
Today, November 24, 2026, the last tunnel boring machine successfully completed its tunnelling work for the Brenner Base Tunnel. Like seven other tunnel boring machines used for the project, it was manufactured by Herrenknecht AG. This marks the completion of the entire eastern main tunnel of what will be the world’s longest underground rail link.
The Brenner Base Tunnel, a 64-kilometer-long key structure of Europe’s rail infrastructure, is being built beneath the Alps between Austria and Italy. As the centerpiece of the Scandinavia-Mediterranean Corridor (SCAN-MED) between Finland in the north and Malta in the south, it will make a significant contribution to the efficiency of Europe’s rail network. Designed as a flat track running deep within the mountain, the Brenner Base Tunnel will allow longer and heavier trains to travel than through higher-altitude summit tunnels. Road transit routes, which are heavily burdened by freight traffic, will benefit from this in particular.
Since 2015, tunnel boring machines (TBMs) manufactured by Herrenknecht AG of Schwanau (Baden-Württemberg) have been in use for the Brenner Base Tunnel.
The construction companies commissioned by the project owner, BBT SE, deployed a total of eight machines to excavate 90 kilometers of the two main tunnels as well as the exploratory and service tunnel. The breakthrough by the tunnel boring machine (TBM)
named “Olga” on November 24, 2026, marked the culmination of the successful tunnelling work for Construction Lot H53 in the east tunnel on the Austrian side. In the west tunnel, the H53 Brenner Base Tunnel construction consortium—comprising the companies PORR and Marti—had already successfully completed mechanized tunnelling in September 2026.
A moving and pioneering moment
The founder and CEO of Herrenknecht AG, Dr.-Ing. E.h. Martin Herrenknecht, made a point of being on site to witness the breakthrough: “A moment that truly moves me! My deepest respect and heartfelt thanks go to everyone who contributed to this magnificent success: BBT SE as the project owner, the companies PORR and Marti with their tunnelling crews, and, last but not least, our teams in Schwanau and on the
jobsite.”
Bernhard Wienhold, the responsible senior project manager at Herrenknecht AG, reflects on the milestone from a technological perspective: “The tunnelling operations for Lot H53 and for the subsequent construction phases serve as a pioneering benchmark for long-distance tunnelling in hard rock. The Follo Line project in Norway or the major Alpine crossings—the Gotthard Base Tunnel in Switzerland, the Brenner
Base Tunnel, and, in the future, the Mont-Cenis Base Tunnel between France and Italy—demonstrate how, together with our long-standing partners, the specialized construction companies, we are gradually pushing the boundaries of what is technically feasible.”
Hard rock specialists
The construction consortia ordered from Herrenknecht tunnelling technology specifically meeting the requirements of their respective tunnel sections: On Lot H53, two Double Shield TBMs with a diameter of 10.33 meters were deployed. Here, the construction teams achieved peak performances of over 600 meters of tunnel per month using Olga. On Lot H41, which runs further north toward Innsbruck, the construction companies used two Single Shield TBMs with a diameter of 10.25 meters for tunnelling the main tunnels. On the Italian side, two Double Shield TBMs with a diameter of 10.65 meters excavated the main tunnels. A Gripper TBM (diameter 7.91m) and a Double Shield TBM (diameter 6.80 m) excavated 16.6 and 14.2 kilometers, respectively, of the exploratory and service tunnel running 12 meters below the main tunnels.
Optimized Processes
In addition to the tunnel boring machines, the Herrenknecht Group’s deliveries included the following equipment: navigation systems for the TBMs (VMT GmbH), invert segment moulds (Herrenknecht Formwork), tunnelling personnel (Global Tunnelling Experts B.V.), as well as moulds for segment production and the lining of conventionally driven tunnel sections, and handling equipment (Euroform S.r.l.).
In cooperation with its subsidiary, H+E Logistik GmbH in Bochum, Herrenknecht supplied and installed a high-performance conveyor belt system for the Brenner tunnel construction project. The conveyor system is designed to handle up to 5,000 metric tons of rock per hour, which is equivalent to the capacity of 190 trucks, each carrying a 26-metric-ton load.
PROJECT DATA BRENNER BASE TUNNEL
› Client: Brenner Basistunnel BBT SE (BBT)
› Contractors:
ARGE H33 Tulfes-Pfons (STRABAG AG, Webuild S.p.A.)
ARGE H61 Mauls 2–3, BTC S.c.a.r.l. (Webuild S.p.A., Ghella S.p.A., P.A.C. S.p.A., Cogeis S.p.A.)
ARGE H41 Sillschlucht-Pfons (Implenia Österreich GmbH, Implenia Schweiz AG, Webuild S.p.A, CSC
costruzioni SA)
ARGE H53 Brenner Basistunnel (Porr Bau GmbH, Marti GmbH Österreich, Marti Tunnel AG Schweiz)
› Application: Railway
› Tunnelling length: approx. 90km
MACHINE DATA
› 1x Gripper TBM: Diameter: 7,910mm; Cutterhead drive power: 3,500kW
› 1x Double Shield TBM: Diameter: 6,800mm; Cutterhead drive power: 2,800kW
› 2x Double Shield TBM: Diameter: 10,650mm; Cutterhead drive power: 4,200kW
› 2x Single Shield TBM: Diameter: 10,250mm; Cutterhead drive power: 4,550kW
› 2x Double Shield TBM; Diameter: 10,330mm; Cutterhead drive power: 4,550kW